引用本文: | 袁晶,许全喜,董炳江,王涛,杨成刚.近20年来三峡水库泥沙淤积及其对库区的影响.湖泊科学,2023,35(2):632-641. DOI:10.18307/2023.0219 |
| Yuan Jing,Xu Quanxi,Dong Bingjiang,Wang Tao,Yang Chenggang.Sediment deposition of Three Gorges Reservoir and its impact on the reservoir area in recent 20 years. J. Lake Sci.2023,35(2):632-641. DOI:10.18307/2023.0219 |
|
|
|
本文已被:浏览 3565次 下载 1767次 |
码上扫一扫! |
|
近20年来三峡水库泥沙淤积及其对库区的影响 |
袁晶1, 许全喜2, 董炳江1, 王涛3, 杨成刚1
|
1.长江水利委员会水文局, 武汉 430010;2.长江水利委员会规计局, 武汉 430010;3.长江重庆航运工程勘察设计院, 重庆 401120
|
|
摘要: |
泥沙问题是三峡工程建设与运行中的关键技术问题之一,只有妥善处理好泥沙问题,才能保证三峡工程长期有效使用,维持水库功能的全面发挥。本文首先结合实测水文、河道地形观测资料,对三峡水库运行近20年来的泥沙淤积特性及水库排沙比进行了较为全面的分析研究,并与已有研究成果进行了对比;其次,围绕防洪、航运以及坝前段的泥沙淤积等方面,进一步分析了水库淤积产生的影响。结果表明:三峡水库蓄水以来,在不考虑区间来沙的情况下,三峡水库共淤积泥沙20.484亿t,近似年均淤积1.102亿t,水库排沙比为23.6%,水库年均淤积量为原论证预测值的33%。其中,库区干流段累计淤积泥沙17.835亿m3(变动回水区冲刷0.694亿m3;常年回水区淤积18.529亿m3),淤积在水库防洪库容内的泥沙为1.648亿m3(干、支流分别淤积1.517亿m3和0.131亿m3),占水库防洪库容的0.74%,“十一五”攻关阶段研究得出的多年平均淤积量及排沙比较实测值均偏大,变动回水区冲淤则出现反向的情况,主要原因是研究采用的入库沙量偏大以及近期河道采砂和水库优化调度等影响。水库淤积对防洪库容和地下电厂的影响尚小,对库区部分水道航道条件产生了一定的影响,应加以关注。 |
关键词: 三峡水库 水库淤积 排沙比 防洪库容 航运 |
DOI:10.18307/2023.0219 |
分类号: |
基金项目:国家自然科学基金项目(U2040218)、三峡后续项目(2136902)和三峡水库科学调度关键技术研究项目(0704198)联合资助。 |
|
Sediment deposition of Three Gorges Reservoir and its impact on the reservoir area in recent 20 years |
Yuan Jing1, Xu Quanxi2, Dong Bingjiang1, Wang Tao3, Yang Chenggang1
|
1.Bureau of Hydrology, Changjiang Water Resources Commission, Wuhan 430010, P. R. China;2.Planning Bureau of Changjiang Water Resources Commission, Wuhan 430010, P. R. China;3.Changjiang Chongqing Shipping Engineering Survey and Design Institute, Chongqing 401120, P. R. China
|
Abstract: |
Sediment problem is one key technical issue in the construction and operation of the Three Gorges Project. Only by properly handling the sediment problem can we ensure the long-term effective use of the Three Gorges Project and maintain a full play of the reservoir function. In this paper, the characteristics of sediment deposition and the sediment discharge ratio of the Three Gorges Reservoir (TGR) in the past 20 years have been comprehensively analyzed and studied based on the observed hydrological and river topographic data, and compared with the existing research results; Secondly, the influence of reservoir sedimentation is further analyzed in terms of flood control, navigation and sediment deposition in front of the dam. The results show that since the TGR impoundment, the total sediment deposition of the TGR is 2.0484 billion tons, approximately 110.2 million tons per year, the sediment discharge ratio of the reservoir is 23.6%, and the average annual sediment deposition of the reservoir is 33% of the original demonstration prediction value without considering the sediment from the interval. Among them, the accumulated sediment deposition in the main stream section of the reservoir area is 1.7835 billion m3 (69.4 million m3 scoured by the fluctuating backwater area; 1.8529 billion m3 silted by the perennial backwater area), and the sediment deposition in the reservoir flood control storage capacity is 164.8 million m3 (151.7 million m3 silted by the main stream and 13.1 million m3 silted by the tributary respectively), accounting for 0.74% of the reservoir flood control storage capacity. The average annual sediment deposition and sediment discharge measured during the 11th Five Year Plan period are relatively large, the scouring and silting in the fluctuating backwater area are reversed, mainly due to the influence of the large amount of sediment entering the reservoir, the recent sand mining in the river channel and the optimal operation of the reservoir. The influence of reservoir siltation on flood control storage capacity and underground power plant is still small, and it has a certain impact on some waterway conditions in the reservoir area, which should be paid attention to. |
Key words: Three Gorges Reservoir reservoir siltation sediment discharge ratio storage capacity for flood control shipping |
|
|
|
|